Reduced Cooling Down

Valid for following frames: SGT5-4000F (V94.3A), SGT6-4000F (V84.3A), SGT5-2000E, SGT6-2000E

12 h reduction
  • Outage time reduction: Rotor cooling down time is reduced from 24 to 12 hours

  • Earlier start of planned maintenance activities

General Product Information

Shorten your shut-down

Availability is one of the key factors for profitability of a power plant. Siemens offers a broad range of products that increase the availability. One of them is the Reduced Cooling Down upgrade. This upgrade is based on a new cooling down procedure, which, amongst others, includes specific alternating speed ranges. These speed ranges increase the cooling air mass flow which results in a reduced rotor cooling time. Thus, the possibility of an earlier start of planned maintenance events or short-dated inspections is provided. Furthermore, RCD leads to a time reduction for gas turbine balancing work at the end of outages.

Thanks to the outage time reduction, the gas turbine availability is extended and a high monetary benefit can be obtained.

Your benefits

Benefits may include:

  • Rotor cooling down time is reduced from 24 to 12 hours
  • Outage time reduction 
  • Short-dated inspections possible
  • Earlier start of planned maintenance activities

Scope of Supply

The scope of this upgrade includes:

  • Modification of instrumentation & control software 
  • Modification of start frequency converter software
  • Preparation during operation possible, finalization and logic function test during the next planned shutdown